Irrigation Engineer Design ofIrrigation Canals Instructional Objectives On completion of this lesson, the student shall learn about: 1. The basics of irrigation canals design 2. The procedures followed to design unlined and lined canals 3. Methods for subsurface drainage of lined canals 3.7.0 Introduction The entire water conveyance system for irrigation, comprising of the main canal, branch canals, major and minor distributaries, field channels and water courses have to be properly designed. The design process comprises of finding out the longitudinal slope of the channels and fixing the cross sections. The channels themselves may be made up of different construction materials. For example, the main and branch canals may be lined and the smaller ones unlined. Even for the unlined canals, there could be some passing through soils which are erodible due to high water velocity, while some others may pass through stiff soils or rock, which may be relatively less prone to erosion. Further, the bank slopes of canals would be different for canals passing through loose or stiff soils or rock. In this lesson, we discuss the general procedures for designing canal sections, based on different practical considerations. 3.7.1 Design of lined channels The Bureau of Indian Standards code IS: 10430 -1982 Criteria for design of lined canals and guidelines for selection of type of |ining (Reaffirmed in 1991) recommend trapezoidal sections with rounded corners for all channels-small or large. However, in India, the earlier practice had been to provide triangular channel sections with rounded bottom for smaller discharges. The geometric elements of these two types of channels are given below: Version 2 CE IIT, Kharagpur Triangular section F:Ir3us,.E l KTriangular channel section For triangular section, the following expressions may be derived A=D2(..c0t ) P=2DLpm (1) ) (m R=D/2 (m The above expressions for cross sectional area (A), wetted perimeter (P) and hydraulic radius (R) for a triangular section may be verified by the reader. Trapezoidal section §:E:i.JRE Trapezoidalr channel section For the Trapezoidal channel section, the corresponding expressions are: A=BD+DH mt) (M Version 2 CE IIT, Kharagpur P=B+2DL cot ) (5) R=A/P The expressions for A and P may, again, be verified by the reader. In all the above expressions, the value of IS in radians. The steps to be followed for selecting appropriate design parameters of a lined irrigation channel, according to IS: 10430 may be summarized as follows: 1. Select a suitable slope for the channel banks. These should be nearly equal to the angle of repose of the natural soil in the subgrade so that no earth pressure is exerted from behind on the lining. For example, for canals passing through sandy soil, the slope may be kept as 2H: 1V whereas canals in rm clay may have bank slopes as 1.5H: 1V canals cut in rock may have almost vertical slopes, but slopes like 0.25 to 0.75H: 1V is preferred from practical considerations. 2. Decide on the freeboard, which is the depth allowance by which the banks are raised above the full supply level (FSL) of a canal. For channels of different discharge carrying capacities, freeboard are given in the following table: Type of Channel Main and branch the values recommended Discharge Freeboard m3/s m for canals Branch canals and major distributaries Major distributaries Minor distributaries Water courses 3. Berms or horizontal strips of land provided at canal banks in deep cutting, have to be incorporated in the section, as shown in Figure 3. NATURAL SLtFm:E. LEVEL F1e:2m:tE 3. Berms for canal banks at deep cutting Version 2 CE IIT, Kharagpur The berms serve as a road for inspection vehicles and also help to absorb any soil or rock that may drop from the cut-face of soil or rock of the excavations. Berm width may be kept at least 2m. If vehicles are required to move, then a width of at least 5m may be provided. 4. For canal sections in filling, banks on either side have to be provided with sufficient top width for movement of men or vehicles, as shown in Figure 4. .39..-mr~ai< me SAME we w'lmH twime mT,_mAL $.L!RFAl§E LEVEi F«lfZ§L}RE £1.{lanai tseation tting The general recommendations for bank top width are as follows: Discharge (m /s) Maximum bank to width m banks 0.15 to 7.5 7.5 to 10.0 10.0 to 15.0 15.0 to 30.0 Greater than 30.0 Next, the cross section is to be determined for the channel section. 5. Assume a safe limiting velocity of flow, depending on the type of lining, as given below: 0 Cement concrete lining: 2.7 m/s 0 Brick tile lining or burnt tile lining: 1.8 m/s 0 Boulder lining: 1.5 m/s Version 2 CE IIT, Kharagpur 6. Assume the appropriate values of flow friction coefcients. Since Mannings equation would usually be used for calculating the discharge in canals, values of Mannings roughness coefficient, n, from the following table may be considered for the corresponding type of canal lining. Surface Concrete Characteristics with surfaces Value of n as: a) Formed, no finish/PCC tiles or slabs b) Trowel float finish 0.015-0.018 c) Gunited finish 0.018-0.022 Concrete bed trowel finish with sides 0.018-0.02 as: 0.019-0.021 a) Hammer dressed stone masonry b) Course rubble masonry 0.018-0.02 c) Random rubble masonry 0.02-0.025 d) Masonry plastered 0.015-0.017 e) Dry boulder lining 0.02-0.03 Brick tile lining 0.018-0.02 7. The longitudinal slope (S) of the canal may vary from reach to reach, depending upon the alignment. The slope of each reach has to be evaluated from the alignment of the canal drawn on the map of the region. 8. For the given discharge Q, permissible velocity V, longitudinal slope S, given side slope , and Manning roughness coefcient, n, for the given canal section, find out the cross section parameters of the canal, that is, bed width (B) and depth of flow (D). Since two unknowns are to be found, two equations may be used, which are: - Continuity equation: Q = A * V (6) - Dynamic equation: V=l(A R23S"2) T1 (7) In the above equations, all variables stand for their usual notation as mentioned earlier, A and R is cross sectional area and hydraulic radius, respectively. Version 2 CE IIT, Kharagpur 3.7.2 Typical sections of lined channels Though there may be a large number of combinations of the factors on which the cross-section of a lined canal depends, some typical examples are given in the following figures, which may give an idea of laying and a practical channel cross section. amaernexi Allclirnensinne inmillimetres FIGURES la). Typical cross section ofcanal when natural ground level isbelow bed level Version 2 CE IIT, Kharagpur 5""" " - mum s K L 1 r.s \ . mum ' T! warm f iy l I IQ !'3-1* H 8slFt'.t1 ' " i r tcawrunmam Lrs . A -., uiihmuhi Alldirnansiotss in millionaires. FIGURE 5lb). Tupical cross section ofcanal when natural ground leuel isbetween canal bedand lullsupply leuels All dimensionsin millintatres FIGURE 5(cc). Typical cross section ofcanal when natural ground level isabove the toplevel oflining Version 2 CE IIT, Kharagpur All ¢li:mmxior:s in miliimsires FIGURE 5(d).Tvpical CFOSS sections ofcanals whencanalbedlevelis abovenatural ground level Version 2 CE IIT, Kharagpur DO'I'|E1Jl'IEPK3lT 4395955759 n-' 3 mremmmuazwtxae ll" REGHTBANK ~mu-wanna: EARII1 mamaum;nemszm4ccmvmumosa unease: All dimensions in millirilaires FIGURE 5 (e).Typical crosssections ofcanals whennatural ground levelis between canalbedandfullsupply levels Version 2 CE IIT, Kharagpur acua1mv_mm ummaax FIEGHT BANK Buwm M BHA9E; cam. uquwgnvmnc-xn _un'uAM>t«.i' ' ' at All diiiterasiena in znillitiietms FIGURE 5 if).Typicalcrosssectionsof canalswhennaturalgroundlevelis abovetopofcanallining The Bureau of Indian Standard code IS: 10430-1982 Criteria for design of lined canals and guidelines for selection of type of lining (Reaffirmed in 1991) may generally be used, in addition to special codes like IS: 9451-1985 Guidelines for lining of canals in expansive soils (first revision) (Reaffirmed in 1991), which may be used under particular circumstances. 3.7.3 Subsurface drainage of lined canals Lined canals passing through excavations may face a situation when the canal is dry and the surrounding soil is saturated, like when the ground table is very near the surface. Similar situation may occur for lined canals in filling when the confining banks become saturated, as during rains and the canal is empty under the circumstances of repair of lining or general closure of canal. The hydrostatic pressure built up behind the linings, unless released, causes heaving of the lining material, unless it is porous enough to release the pressure on its own. Hence, for most of the linings (except for the porous types like the boulder or various types of earth linings which develop inherent cracks), there is a need to provide a Version 2 CE IIT, Kharagpur mechanism to release the back pressure of the water in the subgrade. This may be done by providing pressure relief valves, as shown in Figure 6. FL.-5.NGE'OF PRV I ! FLANGEOF HOUSING PIPE ! 1: 3:5 I BROWS ALONG PERIPHERY EQUIDISTANT . Z 9 E 0 .3 u_, 3;, E E | *1 P LININ ' 90;. 53...... :1 ,.......,,; g 2' Is .-7 Lg E g . .30 V PR.vP'IPE -; 9 P E a .- E E 5 g E5 E " ! P E E E P =r_ . = | a 2 an/_PRVHOUSING I. 5 5 PIPE - g g ENDCAP- too 0% o i P » Q o 0 :3E 0 Q 2 2 C: O CI my 2 Q g E a O C D5 cc 5 ~ V I E E I 0110 .0V O F E . <3P or 0 § l2ROWSALONG 0 2 PERIPHERYEQUIDISTANT P o '-:::« § g 5 Il IF 5 . IE» ...... .:e 5 g soc: 0 g E, 1 I . K '3'! '9! END CAP sQ 0 0 DETAILSOFA Pa :3 D -2- g E 000000 g =2~ 6 o E_E........-.iE 16 - D FIGURE 6a. Details of a Pressure Relief Valve (PRV) Version 2 CE IIT, Kharagpur CENTRAL DRAIN PR'\-" LOCATION SIDE DRAIN PRK-LOCATIONS (INCASE NO TRANVERSE DRAIN INBED _F'R\-" LOCATIONI: IN CASE TRANSIVERSE DRAINS ONSLOPE J TRANSVERSEDRAIN ON SLOPE j EI::::I|I::: LONGITUDINAL DRAIN I TRAINW.-'ERSE DRAIN ON SLOPE FIGURE Sb. Possible locations of PRVs The Bureau of Indian Standard code IS: 4558-1983 Code of practice for under design of lined canals (First revision) discusses various methods for relieving uplift pressure below canal linings. 3.7.4 Design of unlined canals The Bureau of Indian Standard code IS: 7112-1973 Criterion for design of crosssection for unlined canals in alluvial soils is an important document that may be consulted for choosing various parameters of an unlined channel, specifically in alluvial soils. There are unlined canals flowing through other types of natural material like silty clay, but formal guidelines are yet to be brought out on their design. Nevertheless, the general principles of design of unlined canals in alluvial soils are enumerated here, which may be suitably extended for other types as well after analyzing prototype data from a few such canals. Version 2 CE IIT, Kharagpur The design of unlined alluvial canals as compared to lined canals is more complex since here the bed slope cannot be determined only on the basis of canal layout, since there would be a limiting slope, more than which the velocity of the flowing water would start eroding the particles of the canal bed as well as banks. The problem becomes further complicated if the water entering the canal from the head-works is itself carrying sediment particles. In that case, there would be a limiting slope, less than which the sediment particles would start depositing on the bed and banks of the canal. In the following sections the design concept of unlined canals in alluvium for clear water as well as sediment-laden water is discussed separately. 3.7.4.1 Unlined alluvial canals in clear water A method of design of stable channels in coarse non-cohesive material carrying clear water has been developed by the United States Bureau of Reclamation as reported by Lane (1955), which is commonly known as the Tractive Force Method. Figure 7 shows schematically shows such a situation where the banks are inclined to the horizontal at a given angle 9. ii. : §??m::+.*§1::::fa-E;:. {}r:E1El:r E : mi Eiswii F;:¬3%._l$%E ?. Traypezsjidéal shaped UN§ll:r7lEd allluvial canal Two particles A and E are an the imdf and bank It is also assumed that the particles A and B both have the same physical properties, like size, density, etc. and also possess the same internal friction angle (D. Naturally, the bank inclination 9 should be less than <13, for the particle B Version 2 CE IIT, Kharagpur to remain stable, even under a dry canal condition. When there is a flow of water, there is a tendency for the particle A to be dragged along the direction of canal bed slope, whereas the particle B tries to get dislodged in an inclined direction due to the shear stress of the flowing water as shown in Figure 8. Ftieures8. Sitearstrass andweight corfnponentts of tghiaipartiséeis A and B on the bed and iba«ni<, ;res:pes:tiveiy The particle A would get dislodged when the shear stress, 2-, is just able to overcome the frictional resistance. This critical value of shear stress is designated as re may be related to the weight of the particle, W, as 7 = W tan ¢ (8) For the particle B, a smaller shear stress is likely to get it dislodged, since it is an inclined plane. In fact, the resultant of its weight component down the plane, W Sin _andthe shearstress(designatedasTC,) wouldtogethercausethe particle to move. Hence, in this case, (z'CS)2+(W sint9)2=[Wcost9]tan¢ (9) In the above expression it must be noted, that the normal reaction on the plane for the particle B is W Cos 6. Eliminating the weight of the particles, W, from equations (8) and (9), one obtains, Version 2 CE IIT, Kharagpur 2 2 rCS2+[ Cb sin] =[Cb cos(9tan¢] r r tan¢ tan¢ This simplifies to 2 0 TCS2 =2-C172 |:COS2 6-Smz J tan ¢ Or 2 TCS=cos6 1tan26 rcb ( tan ¢ 10) As expected, 2' is less than 2', , since the right hand side expression of equation (3) is less than 1.0. This means that the shear stress required moving a grain on the side slope is less than that required to move on the bed. It is now required to find out an expression for the shear stress due to flowing water in a trapezoidal channel. From Lesson 2.9 it is known that in a wide rectangular channel, the shear stress at the bottom,r0 is given by the following expression Q=yRS on Where y is the unit weight of water, R is the hydraulic radius of the channel section and S is the longitudinal bed slope. Actually, this is only an average value of the shear stress acting on the bed, but actually, the shear stress varies across the channel revealed width. Studies interesting conducted to find the variation results, like the variation of shear of maximum channel base (rb) and sides (rs) shown in Figure 9 to 11. stress have shear stress at v T, as T? s L :§w_,,M,.,..w. [WifK 53 3 06 ,2,2; VL 3,; V L L _L.,,,LW.,. Maximum shearstrsssat bed A E 0.4 L, g3 _ K .....m~.« ivlaximumwshear stress ats§d»as 324681!) San FIGURE 9. Variation ufmaximum shear stress forrectangular channai LV (1 S T5 L ,;~»«»~« - -«-«»»-M if -'~""JW E {far / Max:mumL shaar strassat it-a wwww #32 Bih MaximuVm shear s*4::'e.55 atisidas Maximum . Maximum s%1iea.rr.atress at bed shear stressnel: sides Fgegues 11.:Variationof maximumshearstressof trapezoidalshanrael iwitniside temps W ; 2H As may be seen from the above figures, for any type of channel section, the maximum shear stress at the bed is somewhat more than for that at the sides for a given depth of water (Compare 7,, and IS for same B/h value for any graph). Very roughly, for trapezoidal channels with a wide base compared to the depth as is practically provided, the bottom stress may be taken as yRS and that at the sides as 0.75 yRS. Finally, it remains to find out the values of B and h for a given discharge Q that may be passed through an unlined trapezoidal channel of given side slope and soil, such that both the bed and banks particles are dislodged at about the same time. This would ensure an optimum channel section. Researchers have investigated for long, the relation between shear stress and incipient motion of non-cohesive alluvial particles in the bed of a flowing stream. One of the most commonly used relation, as suggested by Shields (1936), is provided in Figure 12. Version 2 CE IIT, Kharagpur LEGEND also: lteleari diameterof parliaiegraizri sizaj G : Relative: Eiansity of particle g :.l§tCi).'§y-Eff?-§§§.§t¥§3 dueto grawiry LL \ fl 3:; ;Ur§itiwa§gi2troisedimer;:. §W9§PV'EM?Mi3T557"3~ *9:Un§iwei=ight.o§gwater 3mi3H3EW5,l is : l¬i¬&ei§13i}54Z1ig§S.f.§{JS§Zf5é ta! water .2.y,....._~ ex«M x K-*"" «N 4! 2. : Srhéslds parameters: %l"llfE§%1l§l'Efl:ifL1!§Clé§E i i;.,[31L,,._._L,..i_...2,.L;z:J..l MMMMMMMMM ..zLz.,;_.t._i_;._g.;J E .-.2» no is/ltilfll ii?! 12,30 %«=d.§.:;l;;a;:;ai5"3 Rf F§c;s.:.%E 12.Gameforincipient motion Swamee and Mittal (1976) have proposed a general relation for the incipient motionwhichisaccurateto within5 percent.Forvs=2650kg/m3andy =1000kg/ m3the relationbetween the criticalshearstressre (inN/m2)diameterof particle ds (in mm) is given by the equation 0.409 df 1+0.177dS The application of the above formula for design of the section may be illustrated with an example. Say, a small trapezoidal canal with side slope 2H: 1V is to be designed in a soil having an internal friction angle of 35° and grain size 2mm. The canal has to be designedto carry10m3/son a bedslopeof 1 in5000. To start with, we find out the critical shear stress for the bed and banks. We may use the graph in figure (12) or; more conveniently, use Equation (12). Thus, we have the critical shear stress for bed, 1, for bed particle size of 2mm as: TC = Tcb =0.155 + 0.409 * 22 ,/1+0.177 * 22 = 1.407 N/m2 Version 2 CE IIT, Kharagpur The critical shear stress for the sloping banks of the canal can be found out with the help of expression (10). Using the slope of the banks (2H: 1V), which converts to_=26.6° 1'05 0 tan2 26.60 _ j=COS 26.6 E Tc}, tan 35 From which, TC,= 0.625x 0.1.4068 = 0.880N/m2 The values for the critical stresses at bed and at sides are the limiting values. One does not wish to design the canal velocity and water depth in such a way that the actual shear stress reaches these values exactly since a slight variation may cause scouring of the bed and banks. Hence, we adopt a slightly lower value for each, as: Allowable critical shearstress forbed10,,=0.9rC,, = 1.266N/m2 Allowable critical shearstressforbanks:03=0.9z'CS = 0.792N/m2 The dimensions of the canal is now to be determined, which means finding out the water depth D and canal bottom B. for this, we have to assume a B/D ratio and a value of 10 may be chosen for convenience. We now read the shear stress values of the bed and banks in terms of flow variable R, the hydraulicradius, canal slope S and unit weight of water y from the figure-correspondingto a channel having side slope 2H: 1V. However, approximately we may consider the bed and bank shear stresses to be y RS and 0.75 y RS, respectively.Further, since we have assumed a rather large value of B/D, we may assume R to be nearly equal to D. this gives the following expressions for shear stresses at bed and bank; Unitshearstressat bed= 7,,= y D S = 9810x D x 1 = 1.962D N/m2per 5000 metre width. Unit shear stress atbankrS=0.75y DS = 0.75x 9810 x Dx 1 = 1.471 D 5000 N/m2permetrewidth. For stability, the shear stresses do not exceed corresponding allowable critical stresses. Thus, (1,,=)1.962D<(rC,,,=)1.266N/m2 or D < 0.645 m and (13=)1.471D<(rCS, =)0.792N/m2 or D < 0.538 m Therefore, the value of D satisfying both the expression is the minimum value of the two, which means D should be limited to 0.538 m, say 0.53 m. Since the B/D ratio was chosen to be 10, we may assume B to be 5.3 m, or say, 5.5 m for practical purposes. For a trapezoidal shaped channel with side slopes 2H: 1V, we have A = D (B+2D)= 3.445m2 And P=B+2\/5D=7.87m D(B+2D) Thus R = A/P B+2v5D = =0.438m For the grain size 2mm, we may find the corresponding Mannings roughness coefficient n using the Strickers formula given by the expression V 25.6 Using the Mannings equation of flow, we have Q = iAR% 5% Fl = 1 0.014 = 2 m3/s x3.445 x0.438% x 1)% 5000 Since the value of Q does not match the desired discharge that is to be passed in the channel,givenin the problemas 100m3/s, we haveto changethe B/D ratio, which was assumed to be 10. Suppose we assume a B/D ratio of, say, k we obtain the following expression for the flow n P A% And substituting known values, we obtain 10 = 0.014 [k.D+2/§D]% 5000 Substitutingthe value of D as 0.53m, as found earlier, it remains to find out the value of k from the above expression. It may be verified that the value of k is evaluates to around 55, from which the bed width of the canal, B, is found out to be 29.15m, say, 30m, for practical purposes. It may be noted that IS: 7112-1973 gives a list of Mannings n values for different materials. However, it recommends thatforsmallcanals(Q<15m3/s),n maybe taken as 0.02. (In the above example, n was evaluated as 0.014 by Stricklers formula). 3.7.4.2 Unlined alluvial channels in sediment laden water It is natural for channel carrying sediment particles along with its flow to deposit them if the velocity is slower than a certain value. Velocity in excess of another limit may start scouring the bed and banks. Hence, for channels carrying a certain amount of sediment may neither deposit, nor scour for a particular velocity. Observations by the irrigation engineers of pre-independence India of the characteristics of certain canals in north India that had shown any deposition or erosion for several years, led to the theory of regime channels, as explained in Lesson 2.10. These channels generally carry a sediment load smaller than 500ppm. The first regime equation was proposed by Kennedy in the year 1895, who was an engineer in the Punjab PWD. Lindley, another engineer in the Punjab proposed certain regime relations in 1919. Later these equations were modifiedby Lacey, who was at one time the Chief Engineerof the UP Irrigation Department. In 1929 he published a paper describing his findings, which have been quite popularly used in India. These have even been adopted by the Bureau of Indian Standards code IS: 7112-1973 Criteria for design of cross section for unlined canals in alluvial soiIs (Reaffirmed in 1990), which prescribes that the following equations have to be used: 0.003f% Q4 s = T, (13) P=4.75./E (14) % R=0.47 (15) Where the variables are as explained below: S: Bed slope of the channel 0: the discharge in m3/s P: wetted perimeter of the channel, in m R: Hydraulic mean radius, in m f: The silt factor for the bed particles, which may be found out by the following formula, in which d5o is the mean particle size in mm. f=1.76(/Q (16) The Indian Standard code IS: 7112-1973 has also recommended simplified equations for canals in certain parts of India by fitting different equations to data obtained from different states and assuming similar average boundary conditions throughout the region. These are listed in the following table. S.No Hydraulic Parameter All Indian Canals 1 8 (Bed slope) 2 P (wetted Perimeter) 3 R H draulic canals canal canals radius It may be noted that the regime equations proposed by Lacey are actually meant for channels with sediment of approximately 500ppm. Hence, for canals with other sediment loads, the formula may not yield correct results, as has been pointed out by Lane (1937), Blench and King (1941), Simons and Alberts on (1963), etc. however, the regime equations proposed by Lacey are used widely in India, though it is advised that the validity of the equations for a particular region may be checked before applying the same. For example, Laceys equations have been derived for non-cohesive alluvial channels and hence very satisfactory results may not be expected from lower reaches of river systems where silty or silty-clay type of bed materials are encountered, which are cohesive in nature. Application of Laceys regime equations generally involves problems where the discharge (0), silt factor (f) and canal side slopes (Z) are given and parameters like water depth (D), canal bed width (B) or canal longitudinal slope (S) have to be determined or Conversely, if S is known for a given fand 2, it may be required to find out B, D and 0. 3.7.5 Longitudinal section of canals: The cross section of an irrigation canal for both lined and unlined cases was discussed in the previous sections. The longitudinal slope of a canal therefore is Version 2 CE IIT, Kharagpur also known or is adopted with reference to the available country slope. However, the slope of canal bed would generally be constant along certain distances, whereas the local ground slope may not be the same. Further in Lesson 3.6, the alignment of a canal system was shown to be dependent on the topography of the land and other factors. The next step is to decide on the elevation of the bed levels of the canal at certain intervals along its route, which would allow the field engineers to start canal construction at the exact locations. Also, the full supply level (FSL) of the canal has to be fixed along its length, which would allow the determination of the bank levels. The exercise is started by plotting the plan of the alignment of the canal on a ground contour map of the area plotted to a scale of 1 in 15,000, as recommended by Bureau of Indian standards code IS: 5968-1987 Guidelines for planning and layout of canal system for irrigation (Reaffirmed 1992). At each point in plan, the chainages and bed elevations marked clearly, as shown in Figure 13. The canal bed elevations and the FSLs at key locations (like bends, divisions, etc) are marked on the plan. It must be noted that the stretches AB and BC of the canal (in Figure 13) shall be designed that different discharges due to the offtaking major distributary. Hence, the canal bed slope could be different in the different stretches. 2.som<2»l l 3.i)0iJi'¬M 1, . 3 CHANELHEADREv3uLATER I W ; I EDWETHQSM SBQE $i_|3!5E':2H:iV , .m03<.M gwaon uzsmisurm gEDWTH:3QM , f:3E:2H:'1' ) Swgglifj V EEDwlTH:1M L . ems $l_0¥5E:1.5H:lv FSL+'l[n.§r EL+me.5 102.}; 104m 103? 100m FlGU,l§a~E 13. Typicai layout of a canal showing bed and canal full supply levels Version 2 CE IIT, Kharagpur The determinationof the FSL starts by calculatingfrom the canal intake, where the FSL is about 1m below the pond level on the upstream of the canal head works. This is generally done to provide for the head loss at the regulator as the water passes below the gate. It is also kept to maintain the flow at almost at full supply level even if the bed is silted up to some extent in its head reaches. On knowingthe FSL and the water supply depth, the canal bed level elevation is fixed at chainage 0.00KM, since this is the starting point of the canal. At every key location, the canal bed level is determined from the longitudinal slope of the canal, and is marked on the map. If there is no offtake between two successive key locations and no change in longitudinal slope is provided, then the crosssection would not be changed, generally, and accordingly these are marked by the canal layout. At the offtakes, where a major or minor distributary branches off from the main canal, there would usually be two regulators. One of these, called the cross regulator and located on the main canal heads up the water to the desired level such that a regulated quantity of water may be passed through the other, the head regulator of the distributary by controlling the gate opening. Changing of the cross regulator gate opening has to be done simultaneously with the adjustment of the head regulator gates to allow the desired quantity of water to flow through the distributary and the remaining is passed down the main canal. The locus of the full supply levels may be termed as the full supply line and this should generally kept above the natural ground surface line for most of its length such that most of the commanded area may be irrigated by gravity ow. When a canal along a watershed, the ground level on its either side would be sloping downward, and hence, the full supply line may not be much above the ground in that case. In stretches of canals where there is no offtake, the canal may run through a cutting within an elevated ground, and in such a case, the full supply line would be lower than the average surrounding ground level. In case irrigation is proposed for certain reaches of the canal where the adjacent ground level is higher than the supply level of the canal, lift irrigation by pumping may be adapted locally for the region. Similarly,for certain stretchesof the canal, it may run throughlocallylow terrain. Here, the canal should be made on filling with appropriate drainage arrangement to allow the natural drainage water to flow below the canal. The canal would be passing over a water-carrying bridge, called aqueducts, in such a case. As far as possible, the channel should be kept in balanced depth of cutting and filling for greatest economy and minimum necessityof borrow pits and spoil banks. The desired canal slope may, at times, is found to be much less than the local terrain slope. In such a case, if the canal proceeds for a long distance, an enormous amount of lling would be required. Hence, in such a case, canal falls Version 2 CE IIT, Kharagpur are provided where a change in bed elevation is effected by providing a drop structure usually an energy dissipater like hydraulicjump basin is provided to kill the excess energy gained by the fall in water elevation. At times, the drop in head is utilized to generate electricity through suitable arrangement like a bye-pass channel installed with a bulb-turbine. EMATU RAL SURF.l1\.¬ E LEVEL win DERECTEDN GF CANAL FLCIW F35.{F~'L.¥LL. SLE§5iPi.r LEVEL) r 1? {EANAL mssss E : svEr%¢aLC:n:.:»xt E CAMLIN g E 5 l A mw-,,m,;m;~,g Ct}TTlNC% -~ ,L ------~«-w«------~>§ li FlLLlNf£a ~~~~~~~~»~+ . l % CEWAL STARTS . s l CANAL}?-I i T SANAL FIGURE1-4».Longitudinal section of a canal assuming no withdrawals in this stretch A typical canal section is shown in Figure 14, for a canal stretch passing through varying terrain profile. Here, no withdrawals have been assumed and hence, the discharge in the entire stretch of the canal is assumed to remain same. Hence, the canal bed slope and water depth are also not shown varying. It is natural that if the canal has outlets in between, the change in discharge would result in corresponding changes in the full supply line. The elevation of the banks of the canal is found out by adding the freeboard depth. Though the free board depth depends upon many factors, the Bureau of Indian standards code IS: 7112-1973 Criteria for design of cross sections for unlined canals in alluvial soils recommends that a minimum free board of 0.5m be provided for canals carrying discharges less than 10m3/s and 0.75m for canals with higher discharges. Version 2 CE IIT, Kharagpur 3.7.6 Important terms =ree Boar : A depth corresponding to the margin of safety against overtopping of the banks accidental due to sudden or improper rise in the water opening or closing level of a channel on account of gates at a regulator of on the downstream. Borrow pits: Specific site within a borrow area from which material is excavated for use is called a borrow pit. Spoil Banks: Piles of soil that result from the creation of a canal, deepened channel, borrow pit, or some similar structure. References: - IS: 10430 -1982 Criteria for design of lined canals and guidelines for selection of type of lining - IS: 4558-1983 Code of practice for under design of lined canals (First revision) - IS: 5968-1987 Guidelines for planning and layout of canal system for irrigation (Reafrmed - 1992). IS: 7112-1973 Criteria for design of cross-section for unlined canals in alluvial soils 0 IS: 9451-1985 Guidelines for lining of canals in expansive soi|s (first revision) - Shields, A (1936) Anwendung der Aehnlichkeitsmechanic und dser tuirbulenz-forchung auf die Geschiebebewgung, Mitteilungen Pruessischen Versuchsanstalt fur wasserbau und Schiffbau, Berlin - der Swamee, P K and Mittal, M K (1976) An explicit equation for critical shear stress in alluvial streams, CBIP Jnl of Irrigation and Power, New Delhi. Version 2 CE IIT, Kharagpur